Construction recapture
Term · Nuclear energy and radiation · MLC-T-NUC-000079
The maximum number of years that could be added to a facility's license expiration date to recapture the period between the date the NRC issued the facility's construction permit to the date it granted an operating license. A licensee must submit an application to request this extension. For further information, see the Staff Requirements Memorandum regarding SECY-98-296, "Agency Policy Regarding Licensee Recapture of Low-Power Testing or Shutdown Time for Nuclear Power Plants."
| Identifier | MLC-T-NUC-000079 |
|---|---|
| Field | Nuclear energy and radiation |
| References | NRC Glossary |
Record as JSON
{
"id": "MLC-T-NUC-000079",
"term": "Construction recapture",
"field": "Nuclear energy and radiation",
"definition": "The maximum number of years that could be added to a facility's license expiration date to recapture the period between the date the NRC issued the facility's construction permit to the date it granted an operating license. A licensee must submit an application to request this extension. For further information, see the Staff Requirements Memorandum regarding SECY-98-296, \"Agency Policy Regarding Licensee Recapture of Low-Power Testing or Shutdown Time for Nuclear Power Plants.\"",
"references": [
"NRC Glossary"
],
"url": "https://mlchart.com/terminology/nuclear/construction-recapture/"
}
Record 79 of 555 in Nuclear energy and radiation terminology (MLC-0119). Request the full dataset.